  • This study intends to analyze the fastest duration on finishing the implementation of Kwitang Office Park due to the most efficient cost, cheapest material but the quality is the same as the initial design, and the feasibility of infestation on the finishing of implementation. The methodology uses the descriptive research methods such as Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT). Result shows that the optimal time required to complete the rest of construction volume is 90 days for preparatory work, 220 days for structural work, 232 days for architectural work, and 398 days for MEP work, while the cost required to accelerate the completion of remaining construction volume is Rp. 315, 890, 000, - for preparatory work, Rp. 11,387,770,000 , - for structural work, Rp. 3,316,489,000, - for architectural work, and Rp. 7,295,022,000, - for MEP work.