ANALISIS FAKTOR-FAKTOR KETERLAMBATAN PELAKSANAAN PROYEK KONTRUKSI GEDUNG BERTINGKAT (Studi Kasus Proyek Palm Regency Apartement & Mall, Ciledug, Tangerang )
ctrlnum |
44661 |
---|---|
fullrecord |
<?xml version="1.0"?>
<dc schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/ http://www.openarchives.org/OAI/2.0/oai_dc.xsd"><relation>http://repository.mercubuana.ac.id/44661/</relation><title>ANALISIS FAKTOR-FAKTOR KETERLAMBATAN PELAKSANAAN PROYEK KONTRUKSI GEDUNG BERTINGKAT (Studi Kasus : Proyek Palm Regency Apartement & Mall, Ciledug, Tangerang )</title><creator>KURNIAWAN, MUHAMAD RUDI</creator><subject>022.3 Buildings/Bangunan</subject><subject>069.22 Planning for Buildings/Merencanakan Bangunan</subject><subject>620 Engineering and Applied Operations/Ilmu Teknik dan operasi Terapan</subject><subject>624 Civil Engineering/Teknik Sipil</subject><subject>624.9 Building, Structure, and Installation/Bangunan, Struktur, dan Instalasi</subject><description>The Palm Regency Apartement & Mall project is a construction project located in Ciledug. Consisting a condominum with 6 floors height, and 2 Apartement towers with 26 floors each. The total area of this project is 34,100 m2. The delay of the construction project means delayed work that has been agreed based on contract. The delay in construction progress, causing an increasing time of complation from the planned project. In its implementation, the construction of the Palm Regency Apartement & Mall Project, faces several obstacles & problems that causing delays. Research methods based on background and problem formulation. The method used in this research is quantitative descriptive approach with questionnaires spread, whit the respondents from PT. PP (Persero) employees, as the main contractor of Palm Regency Apartement & Mall. Then combaining result from the research with S curve. Contains the causes of delay variables. Then all processed using the SPSS software. Research results of data analysis that had been done shown that the delay factors of The Palm Regency project was change factor of design and method which scored total 170 and minus 4.25. From the calculation of partial test with dependent variabel of delay factors, i.e. X1, X2, X3, and X9 or variable, i.e. Material factor, Man Power factor (staff & labor), Equipment factor and Controll and Schedule Factor. Results of simultanously dependent variable of delay factors test, that is X1 and X6 or variable of Material Factor and Enviromental Factor. From Determination Analysis there are independent variable that effect to significant dependent variable, i.e. X1 and X2 or variable, i.e. Material Factor with 33,5 % and Man Power Factor (staff and labor) with 33,7 %. Also validation results from expert, most dominant factor was change of the design that too significant. Keywords: Delays, Projects, Questionnaires, Contruction

Proyek Palm Regency Apartement & Mall adalah sebuah proyek pembangunan
apartement dan mall yang terletak di Ciledug terdiri dari 1 lantai semibasement,
Condominum yang terdiri dari 6 lantai dan 2 Tower masing-masing terdiri dari 26 lantai
plus atap. Luas total dari proyek ini adalah 34.100 m2.
Metode penelitian berdasarkan latar belakang dan rumusan masalah. Metode penelitian
yang digunakan dalam penelitian ini adalah pendekatan diskriptif kuantitatif dengan
penyebaran kuesioner, yang dilakukan kepada responden dalam hal ini adalah staff
karyawan di PT. PP (Persero), Tbk. selaku main kontraktor di Proyek Proyek Palm
Regency Apartement & Mall. Data sekunder yang digunakan adalah data kurva S.
Kuesioner berisi variabel-variabel penyebab keterlambatan. Kemudian data hasil
kuesioner yang merupaka data primer diolah dengan dengan menggunakan bantuan
software SPSS.
Hasil penelitian dari analisis data yang telah dilakukan dapat diketahui bahwa factorfaktor
keterlambatan proyek palm regency yaitu Faktor perubahan (Change) serta
Design & Method dengan skor total 170 dan Nilai Mean 4.25. Dari hasil perhitungan uji
parsial terhadap variabel dependen faktor keterlambatan yaitu X1,X2,X3 & X9 atau
secara variabel yaitu Faktor bahan (Material), Faktor tenaga kerja (Man Power): Staff
& Labor, Faktor peralatan (Equipment) dan Faktor waktu dan kontrol (Schedulling and
Controlling techniques). Dari hasil uji simultan variabel dependen faktor keterlambatan
yaitu yaitu X1 dan X5 atau secara variabel yaitu Faktor bahan (Material) & Faktor
lingkungan (Environment). Dari Analisis Determinasi (R2) terdapat variabel independen
yang berpengaruh variabel bebas terhadap variabel terikat yang signifikan yaitu X1 dan
X2 atau secara variabel yaitu Faktor bahan (Material) dengan nilai 33, 5 % dan Faktor
tenaga kerja (Man Power): Staff & Labor sebesar 33,7 %. Serta dari hasil validasi pakar
faktor yang dominan yaitu faktor perubahan desain yang terlalu signifikan.
Kata Kunci : Keterlambatan, Proyek, Kuesioner, Kontruksi</description><date>2018-09-25</date><type>Thesis:Thesis</type><type>PeerReview:NonPeerReviewed</type><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/1/1.%20HALAMAN%20JUDUL.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/2/2.%20ABSTRAK.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/3/3.%20SURAT%20PERNYATAAN%20SKRIPSI.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/5/4.%20SURAT%20PENGESAHAN%20SKRIPSI.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/4/5.%20KATA%20PENGANTAR.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/6/6.%20DAFTAR%20ISI.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/7/7.%20DAFTAR%20TABEL.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/8/8.%20DAFTAR%20GAMBAR.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/9/9.%20DAFTAR%20LAMPIRAN.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/10/10.%20BAB%20I.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/11/11.%20BAB%20II.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/12/12.%20BAB%20III.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/13/13.%20BAB%20IV.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/14/14.%20BAB%20V.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/15/15.%20DAFTAR%20PUSTAKA.pdf</identifier><type>Book:Book</type><language>ind</language><identifier>http://repository.mercubuana.ac.id/44661/16/16.%20LAMPIRAN.pdf</identifier><identifier> KURNIAWAN, MUHAMAD RUDI (2018) ANALISIS FAKTOR-FAKTOR KETERLAMBATAN PELAKSANAAN PROYEK KONTRUKSI GEDUNG BERTINGKAT (Studi Kasus : Proyek Palm Regency Apartement & Mall, Ciledug, Tangerang ). S1 thesis, Universitas Mercu Buana Jakarta. </identifier><recordID>44661</recordID></dc>
|
language |
ind |
format |
Thesis:Thesis Thesis PeerReview:NonPeerReviewed PeerReview Book:Book Book |
author |
KURNIAWAN, MUHAMAD RUDI |
title |
ANALISIS FAKTOR-FAKTOR KETERLAMBATAN PELAKSANAAN PROYEK KONTRUKSI GEDUNG BERTINGKAT (Studi Kasus : Proyek Palm Regency Apartement & Mall, Ciledug, Tangerang ) |
title_sub |
Proyek Palm Regency Apartement & Mall, Ciledug, Tangerang ) |
publishDate |
2018 |
topic |
022.3 Buildings Bangunan 069.22 Planning for Buildings Merencanakan Bangunan 620 Engineering and Applied Operations Ilmu Teknik dan operasi Terapan 624 Civil Engineering Teknik Sipil 624.9 Building Structure and Installation/Bangunan Struktur dan Instalasi |
url |
http://repository.mercubuana.ac.id/44661/1/1.%20HALAMAN%20JUDUL.pdf http://repository.mercubuana.ac.id/44661/2/2.%20ABSTRAK.pdf http://repository.mercubuana.ac.id/44661/3/3.%20SURAT%20PERNYATAAN%20SKRIPSI.pdf http://repository.mercubuana.ac.id/44661/5/4.%20SURAT%20PENGESAHAN%20SKRIPSI.pdf http://repository.mercubuana.ac.id/44661/4/5.%20KATA%20PENGANTAR.pdf http://repository.mercubuana.ac.id/44661/6/6.%20DAFTAR%20ISI.pdf http://repository.mercubuana.ac.id/44661/7/7.%20DAFTAR%20TABEL.pdf http://repository.mercubuana.ac.id/44661/8/8.%20DAFTAR%20GAMBAR.pdf http://repository.mercubuana.ac.id/44661/9/9.%20DAFTAR%20LAMPIRAN.pdf http://repository.mercubuana.ac.id/44661/10/10.%20BAB%20I.pdf http://repository.mercubuana.ac.id/44661/11/11.%20BAB%20II.pdf http://repository.mercubuana.ac.id/44661/12/12.%20BAB%20III.pdf http://repository.mercubuana.ac.id/44661/13/13.%20BAB%20IV.pdf http://repository.mercubuana.ac.id/44661/14/14.%20BAB%20V.pdf http://repository.mercubuana.ac.id/44661/15/15.%20DAFTAR%20PUSTAKA.pdf http://repository.mercubuana.ac.id/44661/16/16.%20LAMPIRAN.pdf http://repository.mercubuana.ac.id/44661/ |
contents |
The Palm Regency Apartement & Mall project is a construction project located in Ciledug. Consisting a condominum with 6 floors height, and 2 Apartement towers with 26 floors each. The total area of this project is 34,100 m2. The delay of the construction project means delayed work that has been agreed based on contract. The delay in construction progress, causing an increasing time of complation from the planned project. In its implementation, the construction of the Palm Regency Apartement & Mall Project, faces several obstacles & problems that causing delays. Research methods based on background and problem formulation. The method used in this research is quantitative descriptive approach with questionnaires spread, whit the respondents from PT. PP (Persero) employees, as the main contractor of Palm Regency Apartement & Mall. Then combaining result from the research with S curve. Contains the causes of delay variables. Then all processed using the SPSS software. Research results of data analysis that had been done shown that the delay factors of The Palm Regency project was change factor of design and method which scored total 170 and minus 4.25. From the calculation of partial test with dependent variabel of delay factors, i.e. X1, X2, X3, and X9 or variable, i.e. Material factor, Man Power factor (staff & labor), Equipment factor and Controll and Schedule Factor. Results of simultanously dependent variable of delay factors test, that is X1 and X6 or variable of Material Factor and Enviromental Factor. From Determination Analysis there are independent variable that effect to significant dependent variable, i.e. X1 and X2 or variable, i.e. Material Factor with 33,5 % and Man Power Factor (staff and labor) with 33,7 %. Also validation results from expert, most dominant factor was change of the design that too significant. Keywords: Delays, Projects, Questionnaires, Contruction
Proyek Palm Regency Apartement & Mall adalah sebuah proyek pembangunan
apartement dan mall yang terletak di Ciledug terdiri dari 1 lantai semibasement,
Condominum yang terdiri dari 6 lantai dan 2 Tower masing-masing terdiri dari 26 lantai
plus atap. Luas total dari proyek ini adalah 34.100 m2.
Metode penelitian berdasarkan latar belakang dan rumusan masalah. Metode penelitian
yang digunakan dalam penelitian ini adalah pendekatan diskriptif kuantitatif dengan
penyebaran kuesioner, yang dilakukan kepada responden dalam hal ini adalah staff
karyawan di PT. PP (Persero), Tbk. selaku main kontraktor di Proyek Proyek Palm
Regency Apartement & Mall. Data sekunder yang digunakan adalah data kurva S.
Kuesioner berisi variabel-variabel penyebab keterlambatan. Kemudian data hasil
kuesioner yang merupaka data primer diolah dengan dengan menggunakan bantuan
software SPSS.
Hasil penelitian dari analisis data yang telah dilakukan dapat diketahui bahwa factorfaktor
keterlambatan proyek palm regency yaitu Faktor perubahan (Change) serta
Design & Method dengan skor total 170 dan Nilai Mean 4.25. Dari hasil perhitungan uji
parsial terhadap variabel dependen faktor keterlambatan yaitu X1,X2,X3 & X9 atau
secara variabel yaitu Faktor bahan (Material), Faktor tenaga kerja (Man Power): Staff
& Labor, Faktor peralatan (Equipment) dan Faktor waktu dan kontrol (Schedulling and
Controlling techniques). Dari hasil uji simultan variabel dependen faktor keterlambatan
yaitu yaitu X1 dan X5 atau secara variabel yaitu Faktor bahan (Material) & Faktor
lingkungan (Environment). Dari Analisis Determinasi (R2) terdapat variabel independen
yang berpengaruh variabel bebas terhadap variabel terikat yang signifikan yaitu X1 dan
X2 atau secara variabel yaitu Faktor bahan (Material) dengan nilai 33, 5 % dan Faktor
tenaga kerja (Man Power): Staff & Labor sebesar 33,7 %. Serta dari hasil validasi pakar
faktor yang dominan yaitu faktor perubahan desain yang terlalu signifikan.
Kata Kunci : Keterlambatan, Proyek, Kuesioner, Kontruksi |
id |
IOS5909.44661 |
institution |
Universitas Mercu Buana |
institution_id |
134 |
institution_type |
library:university library |
library |
Perpustakaan Universitas Mercu Buana |
library_id |
542 |
collection |
Repository Universitas Mercu Buana |
repository_id |
5909 |
subject_area |
Econmics/Ilmu Ekonomi Communication/Komunikasi Engineering/Ilmu Teknik Measurement/Teknik Desain, Pengujian, Pengukuran, Kualitas, Perawatan, Pemeliharaan, Perbaikan |
city |
Jakarta Barat |
province |
DKI JAKARTA |
shared_to_ipusnas_str |
1 |
repoId |
IOS5909 |
first_indexed |
2019-05-09T00:33:42Z |
last_indexed |
2019-05-09T00:33:42Z |
recordtype |
dc |
_version_ |
1674510780012167168 |
score |
17.538404 |