Perencanaan Scheduling dan Rescheduling dengan Metode Heuristic SPT Guna Meminimumkan Mean Tardiness dan Makespan

Main Author: Kristinawati, Eti
Format: Article info application/pdf eJournal
Bahasa: eng
Terbitan: Department Industrial Engineering, University of Muhammadiyah Malang , 2010
Subjects:
UMM
Online Access: https://ejournal.umm.ac.id/index.php/industri/article/view/240
https://ejournal.umm.ac.id/index.php/industri/article/view/240/254
Daftar Isi:
  • To complete customer's demand so company must make a plan with using production schedule. Some diffrculties usually happen in shop floor level is a new job which is put in a production schedule that have arranged before. So that the old production schedule have to revised by reschedulling. The procedure that be used to schedule the real time production consist of n job m machine is algoritm of Hueristik Dispatching Rule Shorted Processing Time (SPT) method to minimize mean tardiness and makespan.