  • Sheet Pile used as a retaining wall construction. Construction is later expected to prevent scour the water in the river and can make the area surrounding the banks and can make area in musi river look cleanly and beautifully. Sheet Pile on this project will planned in the Desa Bailangu Barat Kab. Musi Banyuasin. Planning of the steel sheet pile using the calculation of steel sheet pile with free end method. In this planning also will plan about project management includes calculation of budget plan (RAB), Description Unit Price Analysis and compensation Network Planning (NWP) to determine the time and squence of work to do and to control the financial progess of the work and to use the curve S. Based on calculation, it can be concluded this steel sheet pile will pile 16 m inside the land and long 200m, the size of the pile cap long 200m, width 0,70 m, and thick 0,80 m. To carry out this project need the budge Rp. 32.100.200.000.